The objective of the Linky SID project (Linky Deployment Information System) is to build the IT infrastructure necessary for the replacement of electricity meters by the new Linky smart meter. The beneficiary of this project is ERDF (Electricité Réseau de Distribution France), a subsidiary of EDF. Steria has been entrusted with the implementation of this project.
Total project duration : 10 months
LThe total cost of the project was 200 man days.
Details of the project :
Problematic
In view of the liberalisation of the electricity market and to homogenise the existing fleet of electricity meters (more than 23 models), ERDF designed the new smart and communicating meter named Linky. It will be deployed in all households in France between 2012 and 2017. A major IT infrastructure is required to complete this long deployment operation.
The main objectives of the project were :
Mission statement
To integrate the “Mobility” team, which is supposed to develop the embedded tool intended for the realization of customer interventions by technicians. Tasks carried out during the mission:
Organization
Integration of a Steria team of 5 people
Main characteristics of the client
ERDF, a wholly-owned subsidiary of EDF, is the operator of the public electricity distribution network covering 95% of mainland France. Its 35,000 employees operate, maintain and develop nearly 1.3 million kilometers of network every day. The company has 33 million customers and carries out more than 10 million operations per year.
Key success factors
Solution features
Business processes covered by the solution
What were the most difficult features to implement ?
Among the most complex functionalities implemented by the speaker we can count :
Technical platform elements
Software package, software or development languages used
Business result
Today, the tool is used in production by more than 4,000 technicians who have appreciated the ergonomics of its user interfaces and the ease of access to information.