The Project consisted in the implementation of the anti-doping platform of the association Athletes for Transparency (AFT). This platform for athletes in all disciplines and at all levels allows them to publish the results of their doping controls.
Total project duration: 10 months
The total cost of the project was 250 man-days.
Details of the project :
Problematic
The Association Athletes For Transparency financially supported by the World Anti-Doping Agency (WADA), the Rhône-Alpes Region and the Drôme General Council is developing a research programme linked to a technical feasibility study of the biological passport desired by WADA.
Enable the registration of athletes and the publication of their analyses
Manage doping control campaigns and results recording
Mission statement
Development of a complete system including :
Organization
For the realization of the project, 4 persons have been allocated :
This contract was executed entirely with Tana Corp resources dedicated to the project.
Main characteristics of the client
The Athletes for Transparency programme was initially a research programme supported by the World Anti-Doping Agency and linked to the pilot study of the technical feasibility of recording biological parameters in an individual database for the indirect detection of doping. This research programme made it possible in particular to assist with the technical implementation of the biological passport.
Today, the AFT programme is designed to provide a forum for volunteer athletes who wish to show their active commitment to the fight against doping.
Conduct of the project
Advice and support role provided throughout the project
Proposed methodology to validate the project steps from a client’s point of view
Proposed project reporting
A monthly steering committee enabled us to steer this long-term project in close collaboration with the client.
Tools chosen for the project management
Project Management: MS Project
Incident follow-up : BugX (based on Mantis) http://www.mantisbt.org/)
Version and configuration tracking: SubVersion (http://subversion.tigris.org/)
Features of the solution
Business processes covered by the solution
What were the most difficult features to implement?
The types of anti-doping analyses and the indicators evaluated in each analysis are very varied and may change even in the short term. In order to avoid having to carry out cycles of source code updates, unit and integration tests, and deployment each time an indicator is changed, we have made the definitions of these analyses and indicators dynamic and therefore easily modifiable.
Technical platform elements
Software package, software or development languages used
After analysis of all the constraints, Tana Corp proposed the realization of a custom application, based entirely on a hybrid solution Microsoft & CMS OpenSource :
Reasons for the choice
Share of pre-existing developments used on which the Supplier has capitalised to complete the project
Libraries of AJAX interface elements already developed internally by Tana Corp.
Challenges and key success factors
Business result